Maintenance and Trouble-Shooting
Full Data Disk & Clearing Data off Gemini PC
Detector Temperatures
Liquid nitrogen level
Cables to the closed-cycle refrigerator(CCR)
Electrical connections to the detectors
Baking the Getter
Powering up the Motion Control System
Trouble shooting the motion control system
Dichroic slide won't move or initialize
Trouble shooting the telescope control system(TCS)
PCT link or PCT error
SBRC Array (B Channel) all 0.0
Vertical bars in SBRC images
Undesirable Software Characteristics
Full Data Disk & Clearing Data of Gemini PC
Gemini's D: disk only has 500 MB of space for data. When the disk is full Gemini will continue to try to take data and will display a message with a blue background saying insufficient disk space. Unfortunately this message gets partially overwritten by the Status message and may be missed by observers, resulting in lost data.
The best thing to do is try to prevent data loss from lack of disk space by clearing data every other day (it is unlikely, though not impossible, that the D: drive will fill up with only two nights of data). To do this safely, do the following:
- On the Gemini PC start windows (if not already in windows) by typing wi.
- Click on the "My Computer" icon and navigate to the D: drive and Gemini folder.
- Confirm that all data on drive has been copied to gouda /data/gemini/.
- If all data on the Gemini PC is not on gouda, carefully follow the directions on the Quick Reference page for FTPing data to gouda's /data/gemini/ directory.
- Use archclear on gouda to make sure all the data are in the archive. Please do not delete the data on gouda until after the Gemini run is complete because the observers will probably still want to copy it to their own computer(s).
- Use the "My Computer" window on Gemini to select all the .FTS files and put them in the Recycle Bin.
- Right click on the "Recycle Bin" icon and select "Empty Recycle Bin."
Detector temperatures:
6 temperatures are routinely monitored using
Lakeshore Cryotronics temperature diodes and displays. The small blue monitor
cycles through 4 diodes, displaying each temperature reading for a few seconds.
A temperature Log Sheet is provided. The four points monitored are
The other Lakeshore monitor shows the second stage (lowest temperature) of the
CCR head (about 11 K) and the temperature of the SBRC array (28 K). This unit
is a servo system set to keep the SBRC array at 28 K.
The most important temperature to check during the night is the LN2
can. If the temperature begins to rise then the LN2 level is too
low. It should not be allowed to warm up more than 10 K, otherwise the
detector temperatures will begin to change and thermal gradients will be set
up in the internal optical bench.
Liquid nitrogen level:
Gauging the LN2 level is best done
by the temperature meter, but the lack of a white boil-off plume clearly
indicates a low level.
The LN2 should be filled at least twice a day, once in
the very late
afternoon just before dinner and again at the end of the night.
Prolonged observations low in the south (below the Celestial Equator)
will result in quite a large spillage of LN2. It is
occasionally necessary to do a refill before dawn in this case. The
LN2 can is "pressure-filled" from a large reservoir using a
metal transfer tube which can be fed into the neck of the can and
down to its base. To reach the instrument, the LN2
reservoir must be set on the rising/mobile platform.
Extreme care is required when the platform is
rising. It is very easy to hit something or trap a cable.
Extreme care is also required when inserting or withdrawing the tube from
the Gemini
LN2 can, since the metal fill tube can damage the baffle in the
neck of the LN2 can.
To execute the fill once the tube is inserted, simply open the valve
on the big canister. Close the valve again when liquid nitrogen starts
to stream from the Gemini fill tube.
Cables to the closed-cycle refrigerator (CCR):
The air-cooled compressor which drives the CCR is attached to the telescope by
means of a poor-man's gimble - a shackle and some bungy cords - and the pair
of 12 ft long high-pressure helium lines from the compressor to the CCR head
are supported by a cord to minimize twisting.
Experience has shown that almost all parts of the sky can be reached
with this arrangement. Nevertheless, some twisting can occur in the
extreme west and the observer should check the
condition of the cables every 15 minutes ore so when the Hour Angle
exceeds 3 hrs west. Excessive twisting can cause small
helium leaks, which can be monitored using the pressure gauge on the
compressor. The gauge should read about 250 psi. If it falls below
this level a bottle of pure helium is available for replenishment.
Electrical connections to the detectors:
The electrical connections to the detector outputs emerge from the
dewar and fan out into four coax cables which go into the long, shiny
preamplifier box. These cables should be considered fragile and
sensitive and should not be touched, especially when the arrays are
powered up and cold. The output sides of the preamps, from which four
white coax cables go to the Gemini Transputer System, are more
robust. These outputs can be connected to an oscilloscope if required.
Baking the Getter:
The getter (desiccant) needs to be baked periodically (approximately
yearly or after the vacuum dewar has been opened). The getter should
only be baked when Gemini is warm and connected to the vacuum pump.
There should be a cable that connects to the heater hermetic Military
connector on Gemini's wall (this cable is stored in the wooden Gemini
Cable box). The other end of the cable terminates with two BNC connectors.
There is usually an adaptor on the BNC end to convert the BNC to a two-prong
straight connector. Only one of the BNC's is connected to a 25 Ohm, 1 Amp
heater resistor. The other is open. Use a meter to verify which one, if
necessary. Put 15 Volts DC across the resistor for 15-20 minutes. If it
has been a while since the last bake, you can go a little longer (e.g.
30 minutes).
Mechanism | Primary Switch | Secondary Switch |
---|---|---|
FPA | 0 degrees -- open | 270 degrees = 72000 steps |
AUX | 0 degrees -- open | 120 degrees = 32000 steps |
LWF | 0 degrees -- blank | 180 degrees = |
SWF | 0 degrees -- blank | 180 degrees = |
Dichroic | K @ LW | K @ SW |
Waveplate Slide | --- | --- |
Waveplate Rotator | 0 degrees | --- |
If wheels are failing to initialize or to fully reach the position requested, one can move the motor controlling that wheel by a few hundred steps at a time to try to get the wheel to the appropriate switch. Motors may be moved by steps rather than position using the "move motor" selection under the "Engineering" menu. If problems persist, notify the IR Lab team.
Finally, aesthetic problems can be solved by rotating the wheels through a small angle. The angle of rotation can usually be calculated from the image on the screen (for example (delta y)/(delta x) = tan(alpha)). Once the angle has been identified, simply go to the engineering menu and select "move motors". It will prompt for a number of steps. Consult the chart below to calculate the number to steps needed to move through a given angle. The same procedure can be used to check that motors are moving from one position to another (see below for the number of steps between positions).
Wheel | Total Steps | Steps/degree | # Positions | Steps/Positions |
---|---|---|---|---|
FPA | 96000 | ~267 | 4 | 24000 |
AUX | 96000 | ~267 | 3 | 32000 |
LWF | 72000 | 200 | 10 | 7200 |
SWF | 72000 | 200 | 10 | 7200 |
Waveplate | 36000 | 100 | --- | --- |
Slide | Steps between Positions |
---|---|
Dichroic | 8800 |
Waveplate | 25000 |
Dichroic slide won't move or initialize:
First make sure motor driver power is ON. If power is on then dichroic
has gotten stuck (most likely in K@LW position). There is no fix for
this at the telescope. The vacuum dewar must be opened up and the
dichroic slide manually fixed. To prevent this
problem, ALWAYS initialize the dichroic motor from the
Engineering - Motor Init menu before moving the dichroic from the
Setup - Motor Setup menu.
Trouble shooting the telescope control system (TCS):
Once in a while there have been problems communicating with the TCS. Normally
there will be an error message at the Gemini prompt saying TCS link not up.
Some things to try are:
PCT link:
If there is a problem with the PCT link, try the PCT reset under the
"Engineering Menu" in the software. If this does not work, it
will be necessary to cycle the power on the front of the transputer
crate. There is a lighted green button that needs to be turned off for
a few seconds and then back on. Reboot Gemini program and start setup
procedure again. If problem still persists then also cycle power on
the back of the motor driver's controller box and the
transputer box (because there is one more transputer in the motor
controller).
If the Gemini software will not start and gives a PCT link error, use the
check program to identify where the problem is. At the DOS C:\ prompt type
check. You should get a table that lists the transputers and the
connection between them. There should be 16 of them, numbered from 0 to 15.
Typical output of the program is
If you are seeing less than this number that is the cause of the problem.
Make sure both the transputer box and the motor driver controller box are
powered on.
If you only see number 0, then the problem is between the PC
and the transputer crate - number 0 is in a plug-in card in the PC. The likely
suspect in this case is the DB25 cable into the back of the PC was not
properly connected.
If the check command gives a Time Out Error, reconnect the DB25 cable
to the back of the PC.
If you see no transputers, then the PC should be rebooted.
With the current 486 PC used to run Gemini (as of 1 Feb 2002), there will
occasionally be trouble communicating with all the transputers, even though
check shows communication to all the transputers. If this is the case
and starting the Gemini software gives a PCT Boot error, reboot the PC.
If you still get the error, then you may also have to cycle power to the
transputer crate and motor controller.
SBRC Array (B Channel) all 0.0:
This is a PCT link problem and is fixed by cycling the power on the transputer
(see above).
Vertical bars in SBRC images:
Vertical bars (each 4 pixels wide) in SBRC chip images indicates
that the chip is warming up. The chip will start warming up if
the temperature controller somehow gets set to the wrong temperature
(i.e. is any temperature other than 28 K) or if the CCR stops working.
Check to make sure the CCR is on, all cables are properly connected,
and that the cold head is working.
Undesirable Software Characteristics:
When running a script double check that the integration time is
sufficiently long enough for the number of co-adds and multireads
chosen. The program will not inform you if the integration time is too
short and will run the script anyway.
To abort a script during an exposure press CTRL F2 and then
CTRL F3. Otherwise, the script will be aborted only after the current
exposure is finished.
If the computer crashes after 12:00am during a run, it will save the
remaining Log Files in a directory on the hard drive named for the
following day.
check 2.2
# Part rate Mb Bt [ Link0 Link1 Link2 Link3 ]
0 T805b-25 0.33 0 [ HOST 1:1 2:1 3:0 ]
1 T800c-20 0.68 1 [ 4:3 0:1 ... 5:0 ]
2 T800c-20 0.66 1 [ 6:3 0:2 ... 7:0 ]
3 T800c-17 0.66 0 [ 0:3 ... ... ... ]
4 T805d-25 0.90 3 [ 8:3 ... ... 1:0 ]
5 T805d-25 0.90 0 [ 1:3 ... ... 9:0 ]
6 T805d-25 0.89 3 [ 10:3 ... ... 2:0 ]
7 T805d-25 0.89 0 [ 2:3 ... ... 11:0 ]
8 T805d-25 0.90 3 [ 9:3 ... ... 4:0 ]
9 T805d-25 0.90 0 [ 5:3 ... ... 8:0 ]
10 T805d-25 0.90 3 [ 12:3 ... ... 6:0 ]
11 T805d-25 0.90 0 [ 7:3 ... ... 13:0 ]
12 T805d-25 0.90 3 [ 14:3 ... ... 10:0 ]
13 T805d-25 0.90 0 [ 11:3 ... ... 15:0 ]
14 T805d-25 0.90 3 [ 15:3 ... ... 12:0 ]
15 T805d-25 0.90 0 [ 13:3 ... ... 14:0 ]
Last modified: Fri Oct 1 01:20:51 PDT 2010
by Elinor Gates